Search
  • Kaitlyn Pibernik

Farnham Sewage Treatment Works

Updated: Oct 28, 2020

The existing raised inlet works structure was fitted with open mesh decking which was not odour tight. Odour containment covers were required to reduce odour omissions from the site as part of a large housing development in the area.


Covers supplied:


Inlet Chamber A concrete chamber 5m x 3m

Screens Area Various channels and chambers around screens

Channels Approximately 50m total length

Detritors 2 no. 7m x 7m

Outlet Chamber A concrete chamber 3m x 3m







18 views0 comments

Recent Posts

See All
  • LinkedIn
  • Twitter Social Icon
  • Facebook Social Icon

CONTACT US:

© 2020 Corporate Engineering Ltd.

GET IN TOUCH:

Tel: 01189701366

Email: sales@grpcovers.com

Corporate Engineering Ltd.

Culham Mill

Little London Road

Silchester

RG7 2PP