The existing raised inlet works structure was fitted with open mesh decking which was not odour tight. Odour containment covers were required to reduce odour omissions from the site as part of a large housing development in the area.


Covers supplied:


Inlet Chamber A concrete chamber 5m x 3m

Screens Area Various channels and chambers around screens

Channels Approximately 50m total length

Detritors 2 no. 7m x 7m

Outlet Chamber A concrete chamber 3m x 3m